HO CHI MINH CITY - TRUNG LUONG EXPRESS WAY

HO CHI MINH CITY - TRUNG LUONG EXPRESS WAY
Date Submitted: 1 năm
PROJECT OVERVIEW

Implementation period

2004 - 2012

Investor

My Thuan Project Management Unit – Ministry of Transport

Construction units

 

  • Civil Engineering Construction Corporation No. 1

  • Civil Engineering Construction Corporation No. 4

  • Truong Son Construction Corporation – Ministry of National Defense

Construction location

From Ho Chi Minh City to Tien Giang Province

Project value 

9,884 billion VND

Road length 

61.9 km

Products used

Mighty RD, Mighty 150

The Ho Chi Minh City – Trung Luong Expressway began construction in 2004 and was completed in 2012. The entire route spans 61.9 km, featuring two automobile lanes and one emergency lane on each side. The total investment amounted to VND 9,884 billion, fully funded by ODA loans.

This was the first expressway in Vietnam, connecting Ho Chi Minh City with Long An and Tien Giang provinces. It significantly improved the flow of goods between the city and the Mekong Delta provinces by reducing travel time between the two endpoints from 90 minutes to just 30 minutes.

The expressway starts in Tan Tuc Town, Binh Chanh District, Ho Chi Minh City, and ends in Chau Thanh District, Tien Giang Province.

Originally designed with a maximum speed limit of 120 km/h, the road has been operated at a practical speed limit of 100 km/h since it opened to traffic.

ICCI’s Contribution

The Investment Construction & Consultancy International Co., Ltd (ICCI) was honored to be entrusted by the Investor, Consultant, and Contractor as the supplier of concrete admixtures for the Ho Chi Minh City – Trung Luong Expressway Project. We consulted with the Contractor, the Consultant, and reviewed the project's technical documentation to recommend the use of our products: Mighty RD and Mighty 150.