PROJECT OVERVIEW | |
Implementation period |
April 2019 – September 2022 |
Concrete manufacturers |
|
Project value | 12,771 billion VND |
Scale | Over 80 km in length, designed for a speed of 120 km/h, including 4 motor vehicle lanes and 2 emergency lanes |
Product used |
MVN SR |
The Van Don – Mong Cai Expressway Project has a total length of 80.23 km, with a total investment of nearly VND 12,771 billion. The project consists of two independent sections: the Van Don – Tien Yen segment, 16 km long, and the Tien Yen – Mong Cai segment, 64 km long.
The Van Don – Mong Cai Expressway is a key component and the final link in forming the complete Hanoi – Hai Phong – Ha Long – Van Don – Mong Cai expressway corridor. Together with the Hanoi – Hai Phong, Hai Phong – Ha Long, and Ha Long – Van Don expressways, it creates a continuous expressway route with a total length of 281 km.
ICCI’s Contribution
The Investment Construction & Consultancy International Co., Ltd (ICCI) was honored to be entrusted by the Investor, Consultant, and Contractor as the supplier of concrete admixtures for the Van Don – Mong Cai Expressway Project. We consulted with the Contractor, the Consultant, and referred to the project’s technical documentation to recommend the use of our product: MVN SR.