The Long Thanh – Dau Giay Expressway starts at An Phu Interchange, Thu Duc City, Ho Chi Minh Province, and ends at Dau Giay Interchange, Thong Nhat District, Dong Nai Province.
Project Overview | |
Implementation period | 2009 - 2015 |
Investor | Vietnam Expressway Corporation (VEC) |
Construction units |
Joint venture of Cienco 6 – Cienco 8 Cienco 4 Concrete Batching Plant, Le Phan Construction Co., Ltd., and others .... |
Construction location | Ho Chi Minh City – Long Thanh – Dau Giay |
Project value | 20.630 billion VND |
Road length | 55.7 km |
Product used | Mighty RD, Mighty 3000PC2 (MVN 3000PC2) |
The Ho Chi Minh City – Long Thanh – Dau Giay Expressway, also known as the Long Thanh – Dau Giay Expressway, began construction in 2009 and was completed in 2015, with a total length of 55.7 km. The project was invested with a total capital of over VND 20,630 billion, funded through loans from the Asian Development Bank (ADB) and ODA loans from the Japan International Cooperation Agency (JICA).
This is a section of the North-South Expressway, connecting Ho Chi Minh City and Dau Giay. This expressway will help increase the speed of goods transportation between the two regions in particular, and the entire country in general, by reducing travel time between the two areas from 2 hours to just 30–40 minutes.
The Long Thanh – Dau Giay Expressway has 4 traffic lanes and 2 emergency lanes, designed for vehicles to travel at a maximum speed of 120 km/h.
ICCI's Contribution
Investment Construction & Consultancy International Co., Ltd (ICCI) is honored to be trusted by the investor, consultants, and contractors as the exclusive distributor of concrete admixtures for the Ho Chi Minh City – Long Thanh – Dau Giay Expressway project. We have consulted with contractors, consultants, and reviewed the project technical documents to advise the contractors on the use of the following products: Mighty RD, Mighty 3000PC2 (MVN 3000PC2).