BA SON BRIDGE - HO CHI MINH CITY

BA SON BRIDGE - HO CHI MINH CITY
Date Submitted: 1 năm
Project Overview

Implementation Period

February 3, 2015 – April 28, 2022

Contractors

Dat Phuong Group Joint Stock Company

Thien An Mechanical and Construction One Member Limited Liability Company

...

Concrete Suppliers

Saigon RDC Co., Ltd

Fico Pan-United Concrete Joint Stock Company

The Gioi Nha Building Materials Supermarket Joint Stock Company

Project Location District 1, Ho Chi Minh City
Scope of Work All project components

Project Value

3,082 billion VND
Scale 1,465 meters in length, 6 traffic lanes
Product Used MVN 3000RC; MVN 3000PC2

 

Thủ Thiêm 2 Bridge, later renamed Ba Son Bridge, commenced construction on February 3, 2015, and was officially inaugurated on April 28, 2022, with a total investment capital of VND 3,082 billion.

The bridge connects District 1 with the Thu Thiem urban area in Thu Duc City, helping to ease traffic congestion on the Thu Thiem Bridge and Thu Thiem Tunnel, both of which have been overloaded in recent years.

 

Ba Son Bridge has a total length of 1,465 meters with six traffic lanes, and features a single asymmetrical cable-stayed span.

ICCI’s Contribution:

Investment Construction & Consultancy International Co., Ltd (ICCI) was honored to be selected and trusted by the project owner, consultants, and contractors as the concrete admixture supplier for the Ba Son Bridge Project.
We collaborated with the contractors, consultants, and referred to the project’s technical documentation to recommend the appropriate use of the following products: MVN 3000RC; MVN 3000PC2.

Zalo